A negative cost variance combined with a negative schedule variance is an indicator of

Respuesta :

Kalahira
Kalahira Kalahira
  • 27-11-2017
Cost variance and schedule variance are indicators of efficiency of a project. Therefore if you have a negative cost variance and a negative schedule variance, then the project is inefficient and you should look into ways to cut costs and save money.
Answer Link

Otras preguntas

why was the reconstruction act of 1867 so important
the lcd for the fractions 1/3, 3/4, 5/32, and 8/9 is
Chief executive of the Roman Republic ?
Lauren works at CDz, the local music store. Lately, she has noticed that Mike, the regional manager, is making more of the decisions for store displays and musi
Lauren works at CDz, the local music store. Lately, she has noticed that Mike, the regional manager, is making more of the decisions for store displays and musi
VO2max is related to which one of the following choices
Which of these statements identifies a difference between Richard the Lionheart and Charlemagne? A. Richard the Lionheart's forces conquered Jerusalem, while Ch
give an example of an open equation
AP US History question: Determine to what extent Jefferson, after entering the White House, maintained or altered his earlier philosophy of government.
Which word in the sentence is the appositive? His cousin Charlie is learning to play guitar. a. learning b. Charlie c. guitar d. cousin D Is def an answer!