A network diagramming technique in which boxes represent activities is known as a(n) _____.

a. pdm

b. cpm

c. adm

d. pert

Respuesta :

StrongBad
StrongBad StrongBad
  • 16-11-2017
PERT is a review technique/tool, so that can't be it. CPM is Critical Path Method, and you can use a PDM or an ADM to chart it. 

The easy way to remember this answer, is that you write on the arrow when using the "arrow diagram method."  

So the answer is "a. pdm" (precedence diagram method).
Answer Link

Otras preguntas

Y=15+36.5x Y=60+28.5x
The slope of a position vs time graph is equal to what
How would you add: 1 9/10 + 3/4=
Which ordered pair is the solution to the system of equations? 2x-5y=-5 x+2y=11
x=2y-12 x= -6y + 20
Explain how place value could be used to find the difference of 4.23 and 2.75
A container holds a combination of nickels and quarters. There are 156 coins in all, and their total value is $21.60. The system of equations models this situat
Name one plot conflict in the great Gilly Hopkins
How to explain 3,482,000,000 in scientific notation
Which ordered pair is the solution to the system of equations? x+3y=12 -4x+3y=-3 A. (0, 4) B. (6, 2) C. (3, 3) D. (0, −1)