In a work breakdown structure, the sequence of tasks in which there is no slack is referred to as:

Respuesta :

Kalahira
Kalahira Kalahira
  • 25-10-2017
Critical path, the sequence of the tasks where there is no slack. Meaning if one task doesn't start on time because another has not yet been completed, there is no down time and there will inevitably be a delay in the project.
Answer Link

Otras preguntas

what is  15.95 in expanded form
Which geographic factors contributed to the decline of Sumer? Choose all answers that are correct. A. Irrigation of the crops led to salinization of the soil. B
use properties to find the sum or product
What was the primary reason France sought to colonize North America?
How was the southern colonies arranged?
Which continent did the Bantu people reside on?
An online music club has a one time registration fee of $13.95 and charges $0.49 to buy each song.If Emma has $50.00 to join the club and buy songs,what is the
if i had to interview martin luther during the renaissance what questions would i ask him
2(k+m) = 5, solve for m
What are ten ways we use wind?