a company planned to finish a project with 80 people in 80 days.if after the initial 10 days,the number of people reduces to 70,by how many days will the project get delayed?​

Respuesta :

Аноним Аноним
  • 17-10-2021

Answer:

10 days delay

Step-by-step explanation:

in ten day 12.5% work done by 80 peoples

then 87.5% work hsas to be done by 70 peoples

the days consoder as 'x'

then( 70/x)*100 = 87.5

1/x = 87.5/7000

x =7000/87.5

x =80

so 70 peoples take 80 days to finish the work

so 10 days delay

Answer Link

Otras preguntas

A _____ may be added to a main verb to make a verb phrase
The programs initiated by the government in the 1930s were collectively called the _____, and helped to grow the U.S. economy out of the Great Depression. New D
What strategy did the united states use against the soviet union to ensure brinkmanship?
what is a plan for how much to spend and how much to save of ones earnings called
Explain why kansas referred to as bleeding.
Answer This Equation: y = 3(5/6)^2 - 5(5/6) + 6. The (x)^2 means to the second power.
What expression represents "5 less than the product of 7 and x"
Galvanized nails are iron nails that have been plated with zinc to prevent rusting. the relevant reaction is zn2 (aq 2e??zn(s for a large batch of nails, a manu
I have to build a box for my scouting project with a volume of 36 cubic centimeters. The base of the box is 6 m long and 2 m wide. How high should I build the b
Spanish conjugation fill in the blank