If the budget at completion for a project is $200,000 and the cost performance index is .5, what is the estimate at completion

Respuesta :

ayfat23
ayfat23 ayfat23
  • 20-10-2020

Answer:

$400,000

Explanation:

Estimate at completion in finance can be explained as forecast cost of a particular project. It can be estimated by using the expression below

Estimate at completion =[Budget at Completion] /(Cost Performance Index)

From the question, our budget at completion for a project = $200,000

cost performance index is = 0 .5,

Then just input the values we have,

Estimate at completion= 200000/0.5

=$400,000

Therefore, Estimate at completion is

$400,000

Answer Link

Otras preguntas

What did greek and roman pastoral poems do?
What actor became politically influential when he publicly opposed communism?
in a protein molecule the number of amino acid molecules may be as few as
How do I manage my time
how does dna lead sientest to better classify organisims
The length of a rectangle is twice its width. if the perimeter of the rectangle is 54 ft , find its length and width.
What is 5-3(7x+8) simplified?
Wages of $8,000 are earned by workers but not paid as of december 31, 2017. depreciation on the company’s equipment for 2017 is $18,000. the office supplies acc
If you have a population of 1013 and 300 people out of that group is what percentage
7 DUI conviction penalties include imprisonment, impounding of your vehicle, __________________, and a felony conviction.