On January 1, Year 1, Big Co. enters into a contract with a customer to build a bridge on the customer’s land for $2,500,000. The construction of the bridge is expected to be completed at the end of Year 3. Big determines that the progress toward completion of the bridge is reasonably measurable using the input method based on costs incurred. At contract inception, Big estimates that the expected total cost of construction will be $1,700,000. Below are the (1) actual costs incurred during each year, (2) expected costs to complete the construction, and (3) amounts billed to the customer: