If 7 workers took 48 days to complete a project in how many days would 12 workers complete the same project

Respuesta :

AL2006
AL2006 AL2006
  • 17-06-2018
7 workers take 48 days to do one full job.

Together, they do (1/48) of the job per day.

Each worker does (1/7) of (1/(48) = 1/(48·7) of the job per day.

12 workers would do (12 / (48·7) = 1/(4·7) = 1/28 of a job per day.

So it would take them 28 days to do one whole job. 
Answer Link

Otras preguntas

Ed bought 4 pieces of salmon weighing a total of 2 kilograms. One piece weighed 4/10 kg, and two of the pieces weighed 5/10 kg each. What was the weight of the
Item 2 What is the volume of this rectangular prism? 26 cubic feet 35 cubic feet 50 cubic feet 105 cubic feet rectangular prism that is 7 feet by 3 feet by 5 fe
what do i multiply by to get 187? 187 is the total
Why do crops ripen quickly in Alaska
A company share was exchanged at 36 pence per share on the stock exchange on the 6 th Oct. 2014. 25% of the value was wiped out from the share in the next day t
How many formula units are in 9.8 grams of calcium hydroxide?
The stepwise procedure generally followed in linguistic investigasas in the investigations of other scientific disciplines is:experiment, hypothesis, observatio
Make x the subject of the formula3(c - bx) = 18​
Cuando se introduce material genético directamente en un órgano enfermo con el objetivo de que recobre su función, ¿qué tipo específico de terapia se está reali
Robespierre made many enemies during his leadership of the National Convention. Explain.