Crashing a project ______. 
A. is speeding up a project's activities to move its completion date forward 
B. is equivalent to cancellation of a project 
C. is the unexpected termination of a project due to an external event (e.g., a natural disaster) 
D. is the unexpected termination of a project due to an internal event (e.g., poor management)