A capital project is being planned with the following information: 
Architectural and Engineering fees $25,000 
Demolition $10,000 
Construction $250,000 
Furnishing and equipment $25,000 
Operations and maintenance $10,000 
Service contract $30,000 
What amount should be placed in the capital budget for this project? 
a) $300,000 
b) $340,000 
c) $370,000 
d) $400,000